Enter your component costs and project assumptions in PVcase Concept to review financial results for a proposed layout. Complete these inputs before saving the scenario if you want them captured with the design.
Before you begin: Apply a layout so Concept can prefill your equipment quantities. See Generating layouts.
Enter component costs
Price fields start blank when you first open Financials, as Concept does not apply default market rates. Enter unit prices based on your project's specific quotes or your company's purchasing assumptions.
- Click Financials in the left sidebar, then click Edit.
- Under CAPEX, review the quantities Concept prefilled for your modules, inverters, transformers, and mounting. Enter the price per unit for each.
- Under OPEX, enter an escalation rate, for example, 2.4.
- Add your fixed operating costs as a dollar amount per year.
- Add your variable costs per megawatt per year. For example, land leases and maintenance.
- Under Financial and energy production factors, enter the economic lifetime, discount rate and performance loss rate.
- Click Save.
Your LCOE updates in the summary at the top and in the financial results.
If you change your components, the prices reset to zero because different components have different prices. Update the prices and click Save. If you keep the same components and only change something like the GCR, your prices stay and only the quantities change.
Review and save the scenario
- Review the calculated capital expenditure (CAPEX) and levelized cost of energy (LCOE) where available.
- Check that the inputs belong to the layout you intend to assess.
- Save a new scenario to retain the layout and its financial inputs together.
Updating financial inputs does not overwrite an already saved scenario. Save a new scenario after making changes.
Evaluate another design
Changing the layout can change component quantities and the resulting costs, even when the unit prices remain the same. Review the financial inputs whenever you choose different components or a different mounting type.
Save each alternative as a separate scenario so you can compare the design and its financial results.
Key financial terms:
- Capital expenditure (CAPEX): Upfront, one-time investment to build or acquire the asset.
- Fixed operating cost (OPEX): Set annual operating cost (e.g., insurance, land leases) regardless of system size or output.
- Variable operating cost (OPEX): Ongoing maintenance cost tied directly to total plant capacity size.
- Escalation Rate: Annual inflation rate applied to increase OPEX over time.
- Financial & Energy Factors: Key variables like energy yield, panel degradation, and discount rate, along with costs, are used to calculate metrics such as LCOE and ROI.
FAQs
Why doesn't my layout show an LCOE?
Concept calculates LCOE after you enter and save your financials.
Why did my prices reset to zero?
You changed your components. Each component has its own price, so enter the new prices and click Save.
Do I need to re-enter prices every time I generate a new layout?
No. If you keep the same components, your prices carry over and only the quantities update.