Save each layout and its financials as a scenario, then compare scenarios side by side to pick the best design.
Before you begin: Apply a layout and enter your financials. See Generating layouts and Financials.
How saved scenarios work
A scenario is a snapshot of the design and inputs at the time you save it. Changes you make afterward do not update that saved snapshot.
To save a scenario:
- Click Scenarios, then click Save scenario.
- Enter a name for your scenario.
- Click Create.
A scenario is a saved snapshot of your design and financial data. To continue working from one, restore it, make your updates, and save them as a new scenario to preserve your changes.
Trying variations
- Change the GCR or other layout settings. Generate again and apply a layout. Your prices stay, and only the quantities change. Save it as another scenario.
- Change components. Generate and apply a layout. The prices reset to zero, so update them in Financials and click Save before saving the scenario.
Comparing scenarios side by side
Once you have saved at least two scenarios, you can evaluate their technical and financial differences in a single view.
- Head over to Scenarios.
- Click Expand (two-arrow icon).
- Click Compare scenarios.
- Select at least two scenarios.
- Click Compare.
Pin a baseline
Set a reference point to easily see how other designs stack up against a control option:
- Find the scenario you want to use as the reference.
- Select its pin control to set it as the baseline.
- Review the other scenarios against that reference.
What gets compared
The comparison table highlights differences across three categories:
| Category | Included Metrics |
| Buildable area |
• Buildable Area size • Buildable percentage (%) |
| Design |
• Frame count • Module count • Lower-tier device count (Inverters or DC combiners) • Top-tier device count (Transformers or Central inverters) • GCR • DC/AC ratio • DC Capacity • AC Capacity • Annual yield • AC specific yield • AC performance ratio • Area size • Excluded area size • Net area size • LCOE (Levelized Cost of Energy) |
| Financial |
• CapEX - cost • OpEx - Fixed operating cost • OpEx - Variable operating cost • OpEx - Escalation rate (%) • Economic lifetime • Discount rate (nominal WACC) • Performance rate loss (PRL) |
If you did not modify the buildable area boundaries between variations, those metrics will remain identical across all scenarios.
Interpret the results
Read the metric names and values when deciding which option suits your project. A higher value is not automatically better for every metric.
For example, a lower levelized cost of energy (LCOE) is favorable when evaluating energy cost. Review that result alongside the design requirements and other assumptions used for the scenario.
If two scenarios use the same unit prices but have different component quantities, their capital expenditure can still differ.
Continue with a scenario
To keep working from a saved scenario, click Restore, make your updates, and save it again as a new scenario to preserve your changes.
Exporting a saved scenario
To export a previously saved scenario, click Restore to make it active first, as exports always pull from your current workspace (see Exporting design and site images).